Synopsis
Oracle is seeking to protect itself from potential cost increases related to a large data center project in New Mexico by sending a “force majeure” notice to the developer, Bloomberg News reported on Thursday, citing sources familiar with the matter.
AgenciesShares of the company fell around 4% in premarket trading after the report, which cited sources familiar with the matter. Reuters could not independently verify it.
Oracle is aiming to delay payments should the data center dubbed Project Jupiter get derailed and fail to come online in 2028 as planned, rather than exiting as the main tenant, according to the report.
Companies typically invoke force majeure to free themselves from contractual obligations when problems arise beyond their control. Oracle and Blue Owl did not immediately respond to Reuters requests for comment.